// our story
// b2b green
// our friends |
|
Wanjai 6 years old, Malandi 8, Chao 9, Pascal 8, Fred 7, Mchenge 6… are part of this group of children who dream of learning in a proper classroom. |
Our project under Education As A Right for 2010
Mwanbilki Nursery School in Kajire Village, Kenya
Mwanbilki nursery school nursery school was set up a couple of years ago by the parents and communities of Kajire, Mwanbikili as children of this area were walking over a hour daily by foot to access Kajire main primary and nursery school.
Kajire is a lovely rural village on the slope of Mount Taveta on the border of the famous Tsavo national park. It has approximately 3000 inhabitants dispersed on a vast area surrounding the park.
The Mwanbilki nursery school had 36 children this year and expecting a dozen more in 2010. They gather every week day in the mud-house church or outside under the shade of a tree. The nursery school is run by its headmaster and an assistant teacher who is currently volunteering.
Communities of this part of the village started laying bricks but need more funding to go on. We are working on this project through Sukumakenya and with your support, we will build this school!
A special fund has been set up and you can donate to this fund by using the donation buttons on this page. There is no fixed amount so go ahead and help out with whatever you can afford.All donated funds will sent in two payments to the project organisers at Sukumakenya . First payment will be July 05 2010 to help them with the building process. Second payment will be in early December 2010.
If you would like to receive email updates on the fundraiser, please enter your email in the donation page and we will send you monthly updates so that you can track the fundraiser.If you havea special message for the children and those that take care of them, please send your message on the donation page and we will forward it to them. Do let us know if you would like a reply to your message.
On behalf of all the folks and children in Kajire, we thank you for your helping hand!
EcoGear.
I/ classroom for the nursery school
Schedule of Materials for Construction of a Standard Classroom
|
NO. |
Description |
UNIT |
QTY |
PRICE |
TOTALS (Ksh) |
A |
SUB-STRUCTURES |
|
|
|
|
1 |
12mm diameter reinforcement bars (Y) |
Pcs |
10 |
980 |
9,800 |
2 |
10mm diameter reinforcement bars (Y) |
Pcs |
21 |
780 |
16,380 |
3 |
Binding wire |
Kgs |
5 |
150 |
750 |
4 |
Ordinary Portland Cement |
Bags |
73 |
700 |
51,100 |
5 |
Ballast ½" |
M3 |
7 |
15000 |
105,000 |
6 |
Sand (River) |
M3 |
7 |
6000 |
42,000 |
7 |
Hardcore |
M3 |
7 |
10000 |
70,000 |
8 |
500 guage black polythene paper |
M2 |
70 |
80 |
5,600 |
9 |
B.R.C.A. 142 mesh |
M2 |
1 |
18000 |
18,000 |
10 |
Gladiator 4TC (anti-termite) |
Ltr |
1 |
3,000 |
3,000 |
11 |
390x200x200mm quarry blocks |
Ft |
390 |
70 |
27,300 |
12 |
Hoop Iron (17x8) |
Roll |
1 |
1800 |
1,800 |
13 |
Pine timber 200x25mm |
L.M. |
35 |
120 |
4,200 |
B. |
SUPER-STRUCTURE |
|
|
|
|
1 |
390X150X150mm machine cut blocks |
No. |
1100 |
70 |
77,000 |
2 |
Ordinary Portland Cement |
Bags |
15 |
700 |
10,500 |
3 |
Sand (River) |
M3 |
7 |
6000 |
42,000 |
4 |
Ballast |
M3 |
7 |
15000 |
105,000 |
5 |
6mm diameter reinforcement bars (R) |
Pcs |
12 |
250 |
3,000 |
6 |
12mm diameter reinforcement bars (Y) |
Pcs |
12 |
980 |
11,760 |
7 |
Binding wire |
Kgs |
5 |
150 |
750 |
8 |
Ordinary nails 3" |
Kgs |
4 |
120 |
480 |
9 |
Ordinary nails 4" |
Kgs |
4 |
120 |
480 |
10 |
75mm diameter G.I. pipe 3m long (black) with "U" shaped to receive 50mm wall plate |
No. |
4 |
2500 |
10,000 |
11 |
Damp proof course |
L.M. |
7 |
450 |
3,150 |
C |
ROOF |
|
|
|
|
1 |
100x50mm Cyprus timber |
LM |
319 |
130 |
41,470 |
2 |
75x50mm Cyprus timber |
LM |
110 |
120 |
13,200 |
3 |
200x25mm fascia boards |
LM |
42 |
180 |
7,560 |
4 |
3.0m long G.I.C. sheets guage 28 |
No. |
16 |
1250 |
20,000 |
5 |
2.5m long G.I.C. sheets guage 28 |
No. |
16 |
1050 |
16,800 |
6 |
2.0m long G.I.C. sheets guage 28 |
No. |
32 |
830 |
26,560 |
7 |
2.0 Ridges cap |
No. |
5 |
190 |
950 |
8 |
Ordinary nails 4" |
Kgs. |
10 |
120 |
1,200 |
9 |
Roofing Nails |
Kgs |
6 |
250 |
1,500 |
10 |
Wood preservative (Black) |
Ltrs |
20 |
800 |
16,000 |
11 |
250mm long by 10mm diameter bolts |
No. |
8 |
150 |
1,200 |
12 |
Ordinary Nails 2" |
Kgs |
5 |
120 |
600 |
D. |
Doors and Windows |
|
|
|
|
1 |
100x50 rebated hardwood door frame size 2700x900mm with 1 mullion bulgar Proofed 12mm diameter Bars |
No. |
1 |
1500 |
1,500 |
2 |
2100x900mm hardwood paneled door |
No. |
1 |
6000 |
6,000 |
3 |
100mm butt hinges |
No. |
3 |
50 |
150 |
4 |
2 Lever union mortice lock |
No. |
1 |
1500 |
1,500 |
5 |
Wood screws |
Pkt |
1 |
150 |
150 |
6 |
Hardwood window frame with R12mm bars size 1500x1500mm high |
No. |
2 |
3500 |
7,000 |
7 |
Hardwood window frame with R12mm bars size 1500x1500mm high |
No. |
3 |
3300 |
9,900 |
8 |
Mesh wire Heavy gauge [sheets] |
No. |
6 |
750 |
4,500 |
E |
FINISHES |
|
|
|
|
1 |
Universal undercoat |
Ltrs |
24 |
700 |
16,800 |
2 |
Plastic emulsion |
Ltrs |
40 |
450 |
18,000 |
3 |
Black Bituminous paint |
Ltrs |
10 |
500 |
5,000 |
4 |
Gloss paint |
Ltrs |
10 |
650 |
6,500 |
5 |
Paint brushes 6" |
No. |
2 |
150 |
300 |
6 |
Paint brushes 2" |
No. |
2 |
80 |
160 |
7 |
Thinner (standard) |
Ltrs |
8 |
200 |
1,600 |
8 |
Transport of goods |
@trip |
5 |
6000 |
30,000 |
9 |
Labour (Kajire) skilled/unskilled |
|
|
|
|
|
TOTAL for 1 classroom |
|
|
|
875,150 |
TOTAL COST IN USD : 11,560.8
2/ Running costs for the school
(Based on an estimate of 50 children in 2010)
Item |
Qty |
Price per Qy in Ksh |
Total |
Furniture - desks |
25 |
3000 |
75000 |
Black board |
2 |
3000 |
6000 |
Stationary for school (basic: chalk, paper, stapler etc..) |
|
|
15000 |
Books as per curriculum |
100 |
300 |
30000 |
Books and pencils for children for year |
50 |
200 |
10000 |
Salary headmaster |
12 |
15000 |
180000 |
Allowance assistant |
12 |
5000 |
60000 |
TOTAL |
|
|
376000 |
TOTAL COST IN USD: 4,966.97
|
|
|